One Risk question???????? [发表于 2003/12/9] 状态 开放帖 浏览量 1389 |
|
Project team A has been hired to manage a transportation project very similar to dozens of projects they've managed successfully in the past. The team has determined that the probability of achieving project objectives is 94%. The team has determined the size of contingency reserves that may be needed. These determinations are included in which process? A. Qualitative risk analysis B. Risk response planning C. Quantitative risk analysis D. Risk identification
|
>>> 由论坛统一发布的广告:
|
|
楼主
Taping

职务 无
军衔 三等兵
来自 不告诉你 :)
发帖 25篇
注册 2003/3/27
PM币 1
经验
|
|
Re:One Risk question????????
[回复于 2003/12/10]
|
B.
|
|
|
1楼
elixiang

职务 无
军衔 一等兵
来自 北京市
发帖 74篇
注册 2003/8/23
PM币 471
经验
|
|
Re:One Risk question????????
[回复于 2003/12/10]
|
B is right see PMBOK ,contigency is determined at risk response process
|
|
|
2楼
horsetiger

职务 无
军衔 三等兵
来自 不告诉你 :)
发帖 17篇
注册 2003/4/10
PM币 119
经验
|
|
Re:One Risk question????????
[回复于 2003/12/10]
|
C probability of achieving project objectives and determined the size of contingency reserves is from C process.
|
|
|
3楼
ping

职务 无
军衔 三等兵
来自 不告诉你 :)
发帖 15篇
注册 2003/12/3
PM币 133
经验
|
|
Re:One Risk question????????
[回复于 2003/12/11]
|
对C有置疑。在实际工作中,不是所有的风险都需要定量分析。但所有的风险都需要在response中做应对。所以,B是正确答案
|
|
|
4楼
horsetiger

职务 无
军衔 三等兵
来自 不告诉你 :)
发帖 17篇
注册 2003/4/10
PM币 119
经验
|
|
Re:One Risk question????????
[回复于 2003/12/12]
|
C. 提干中提到的两点正好是风险定量分析的结果。
|
|
|
5楼
eexam

职务 无
军衔 三等兵
来自 不告诉你 :)
发帖 126篇
注册 2003/7/3
PM币 510
经验
|
|
Re:One Risk question????????
[回复于 2004/1/5]
|
PMBOK P144 contingency reserves amounts needed 是风险应对计划的输出
|
-------------------------------------------------------------------------------------------------------- PM阵营中永远的新兵……
|
|
6楼
Adam

职务 无
军衔 少尉
来自 北京
发帖 418篇
注册 2003/2/17
PM币 439
经验
|
|
Re:One Risk question????????
[回复于 2004/1/5]
|
图在PMBOK P140,说明在P144 Contingency reserves amounts needed is one of Risk response Planning' outputs. B is correct!
|
-------------------------------------------------------------------------------------------------------- 地球是靠乐天派来推动的! http://davidwzp.blog.163.com
|
|
7楼
davidwzp

职务 无
军衔 上士
来自 北京
发帖 654篇
注册 2003/12/1
PM币 4767
经验
|
|
Re:One Risk question????????
[回复于 2004/1/5]
|
Confused: 一、probability is the output of quantitative risk analysis 11.4.3 Output from quantitative risk analysis 3.Probability of achieving the cost and time objectives The pobability of achieving the cost and time objectives under the current plan and the current knowladge of risksfacing the project can be estimated using quantitative risk. 二、contingency reserves is one of the content of risk reponse plan 11.5.3 Outputs form risk response planning 1.risk response plan:the risk reponse plan should be writen to the level of detail at which the action will be taken.It should include some or all of the following. …… Contingency plans and fallback plans
|
|
|