以下是北京现代卓越的test 主要是成本管理方面的,请各位高手指教,不明为什么?多谢! 一、 COST MANAGEMENT 1. During the execution of a project, a large number of changes are made to the project. The project manager should? A. Wait until all changes are known and print out a new schedule B. Make changes as needed but retain the schedule baseline C. Make changes as needed D. Talk to management before any changes are made 2. Value Engineering/Analysis is the systematic use of techniques which does NOT : A. establish value for required functions B. provide the required functions at the lowest cost C. identifies the required functions at the lowest cost D. seeks to trade performance to cost 3. The cumulative CPI has been shown to be relatively stable after what percentage of project completion? A. 5% to 10% B. 15% to 20% C. 25% to 35% D. 50% to 75% 4. EVM(Earned Value Management) enables use to get useful information on project performance.Which of the following is less reliable compared to the others? A. Project performance trend B. Forecasting project completion C. Expected project budget D. Project performance 1。B 2.D 3.B 4 .B
|