80. You have inherited a project that is in trouble. The team members are spread out in S states, the schedule is behind by 20%, the former project manager alienated the team and there is no conmunication plan. The first issue you must work on is building a cohesive team to get the project back on track. Which of the following is not a technique that you would use in team development: A. Flying everyone in for a team meeting B. Provide training for those areas that are suffering the most C. Establish a reward system that will pay out based on getting the critical path back within the established time frame D. Use perfonmnce reports to get feedback on individual perfonmnce
I prefer A 0r D, but seems D is an input not a technique. what is your suggestion?