All the following are purpose of project risk management except a. Identifying factors that are likely to affect the project scope, quality, time and cost b. Developing response strategies for all identified risks c. Providing a baseline for project factors that cannot be controlled d. Mitigating impacts by influencing project factors that can be controlled
应该选B。请注意“Developing response strategies for all identified risks”中的“all”。项目风险管理并不对“所有已识别的风险”开发应对策略,而对确实影响项目要素的风险采取应对策略。风险识别后还要进行风险的定性和定量分析,某些风险量极低,或者项目的时间紧迫,即制定风险应对策略的成本相对较大时,就不必制定风险应对策略。另外,风险定性分析后,可能根据项目总体风险评级决定终止项目,就不必制定风险应对策略了。 以上意见当否,请各位指正。