The Scope Management Plan is included in which of the following documents? a.Project plan b.The Work Breakdown Structure c.The Scope Statement d.Project specifications
A complete and through product desciption is critical to the development of a concise scope statement. This description should include all but which of the following: a.detailed enough to support later project planning b.detailed budget and functionality information c.relationship between the product/service being created and the business need d.strategic alignment with corporate objectives
To prepare for scope approval for a project, the PM will need to provide management with all but which of the following: a.the detailed project plan b.specifications c.technical documentation d.fully of partially completed deliverables e.approved project budget f. a and e 为了准备项目范围的审批,项目管理将要提供除了下面哪项以外的管理? A.详细的项目计划 B.规范 C.技术文档 D.完整的或部分完成的交付物 E.批准的项目预算 F. A和E