22. You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is: 1. the project is operating at a favorable cost efficiency ratio. 2. the project is spending more than planned 3. the project is behind schedule. 4. the project is ahead of schedule. 5. B and C