10.The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you are managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It’s too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule. 项目出资人使你陷入了一个两难的处境。CEO已经在年度股东大会上宣布你正在进行的项目将在本年年底完成。问题是,这样就要求要比原来进度规定的完成日期提前六个月完成。返回去再去纠正她的错误已经来不及了,而且股东们也正期待着项目在CEO宣布的日期完工呢。你必须提前这个项目的交付日期。这件事发生之前,你的主要制约因素就是预算。你可以采取什么措施来加速项目的完成。 A. 采用更多的资源以使工作更快地完成。 B. 申请更多的资金以使你可以将原定由内部资源完成的项目阶段改为外部完成。 C. 利用谈判和影响技巧说服项目出资人去劝说CEO并对她的宣告做出修正。 D. 检查项目计划看看是否有能够快速跟进的阶段,如果有就修改计划来反映进度压缩。
|
>>> 由论坛统一发布的广告:
|
|
楼主
guojiayoung

职务 无
军衔 上士
来自 辽宁省
发帖 2211篇
注册 2004/4/9
PM币 1893
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/8/29]
|
D
|
|
|
1楼
莉莉

职务 无
军衔 无军衔
来自 不告诉你 :)
发帖 116篇
注册 2004/8/15
PM币 256
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/8/30]
|
猜 b
|
|
|
2楼
eveningstar

职务 无
军衔 一等兵
来自 上海
发帖 1689篇
注册 2004/4/7
PM币 1361
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/8/30]
|
B
|
-------------------------------------------------------------------------------------------------------- 如果我只剩下一分钱 我要把它 抛向蓝天 去买 一份快乐 然后 与你分享
|
|
3楼
shsjsj

职务 无
军衔 二等兵
来自 上海市
发帖 24篇
注册 2004/8/20
PM币 96
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/8/30]
|
eveningstar 、shsjsj :说说为什么? 我认为是:D。
|
|
|
4楼
guojiayoung

职务 无
军衔 上士
来自 辽宁省
发帖 2211篇
注册 2004/4/9
PM币 1893
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/9/1]
|
答案是什么? 只是感觉,错了就不用说为什么了:)
|
|
|
5楼
eveningstar

职务 无
军衔 一等兵
来自 上海
发帖 1689篇
注册 2004/4/7
PM币 1361
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/9/1]
|
我选D 谁来公布和解释一下正确答案呢
|
-------------------------------------------------------------------------------------------------------- 说醒时只缘醉... MSN : lavenderhyh@hotmail.com 主页: http://lavenderhyh.blogchina.com
|
|
6楼
lavender_hyh

职务 无
军衔 上校
来自 不告诉你 :)
发帖 966篇
注册 2004/7/15
PM币 5651
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/9/1]
|
认为应该是D, 最大的制约是预算,则“更多的资源”和“更多的资金”是不可获取的,首先排除C,
|
|
|
7楼
sign

职务 无
军衔 三等兵
来自 不告诉你 :)
发帖 15篇
注册 2004/9/1
PM币 119
经验
|
|
Re:[讨论] PMP备考经典练习10
[回复于 2004/9/2]
|
D。因为有限制Your primary constraint before this occurred was the budget
|
--------------------------------------------------------------------------------------------------------
|
|