3. A project manager states, “I know that the risk exists and am aware of the possible consequences. I am willing to wait and see what happens. I accept the consequences should they occur. ” He /she is exercising the method of risk reduction. A. Transfer B. Avoidance C. Mitigation D. Assumption 某项目经理说,"我知道有风险存在,而且注意到其可能的后果我愿意等着看会发生什么事万一他们确实发生,我接受其结果" 他对于减少风险是在用什么方式 A. 转移 B. 回避 C. 降低 D. 接受 答案D:很显然是被动接受风险。
4. A project manager states, “I will take the necessary measures required to control this risk by continuously reevaluating it and developing contingency plans or fall-back positions. If the risk event occurs, I will take the appropriate actions.” He/she is exercising the method of risk reduction. A. Transfer B. Avoidance C. Mitigation D. Acceptance 某项目经理人说," 我将会采取必要的措施去控制风险, 通过不断地反复评估风险, 制定应变计划或重做 如果风险事件确实发生, 我将会采取适当的行动"该经理是在运用什么方式去减少风险 A. 转移 B. 回避 C. 降低 D. 接受 答案C,我选择的是D.contingency plans or fall-back 分明是主动接受的措施。