I1.20.誰对项目的可交付成果负主要责任? A.质量经理B项目经理C个人D高级管理层 1.20.who takes the primary responsibility for project deliverables? b.PM,c.individuals 为什么是个人?这里说的是deliverables. --- I1.22.CCS不包括下面什么? C.对CCB权利与责任的描述 D项目进行期间控制系统的执行程序. 1.22.CCS should include all the following except c.A description of the powers and responsibilities of the CCB d.procedures for conducting a mid project control system review
--- I2.9需要重新制定基准计划的原因可能是? B.提供真实的数据对绩效进行测量 C.报告更新的进度计划 2.9Re-baselining may be needed to b.provide realistic data to measure performance c.report schedule updates 答案是B,为什么?
---===
I2.23一个项目失去控制,你被任命为新PM,要求你对项目的质量水平进行核实并采取纠正措施,你首先应该做什么? A.审核项目计划 B.绘制控制图 C.召开头脑风暴会义 D.建立一份风险减轻计划 2.23a project is out of control and you are replaced as a new project manager.you are asked to verify the quality level of the project and to take corrective action.what will you first do? A.review the project plan b.draw a control chat c.have a brainstorming meeting d.create a risk mitigation plan 是B,为什么?控制图不是对审核过程结果进展情况的吗?我想应该是A,或直接一些是C?
P2.1审查规范的完整性是在下列哪个周期中执行? A.奖励B.要求C.申请D.询价 P2.1the review for the specification completeness is performed during which of the following cycies? A.award B.requirements C.requisition D.solicitation 是D.为什么?不知所云,这个题出的是什么意思?