32. Elements of changing a project schedule include all of the following EXCEPT: A. Obtain the appropriate levels of approval. B. Submit the appropriate change requests. C. Evaluate the impact of a change to the schedule. D. Adjust the project end date to the schedule variance. 变更项目进度的要素不包括下列哪一个: A. 获得适当的认可水平 B. 提交适当的变更请求 C. 评估进度变更的影响 D. 根据进度偏差调整项目完工日期 33. An individual’s willingness to take a risk can be determined by: A. Decision tree modeling. B. Monte Carlo method. C. Sensitivity analysis. D. Utility function. 一个个人愿意接受风险的程度是由什么决定的: A. 决策树模型 B. 蒙特卡洛分析 C. 敏感度分析 D. 效用分析 37. Scope change control MUST be integrated with all of the following control processes EXCEPT: A. Schedule B. Cost C. Procurement D. Quality 范围变更控制必须与下列控制过程整合起来,但不包括: A. 进度 B. 成本 C. 采购 D. 质量