15. The most important element necessary for project control is- 项目控制中最重要的因素是 [ ] a. Upper management commitment 上层管理的投入程度 b. Responsibility over resources 对资源负责 c. Clear requirements 有明确的要求 d. Sufficient management reserve 充足的管理准备金 16. Which term describes a modification of a logical relationship that delays a successor task? 下列哪个名词描述了导致下一项任务延迟的逻辑关系的改变?[ ] a. Lag 落后 b. Lead 领先 c. Float 时差 d. Slack 浮动时间 17.A diagram that ranks defects by frequency of occurrence is a: 按发生频率排列缺陷的图表是:[ ] A. Checklist 一览表 B. Decision tree 决策树 C. Cause and effect diagram 因果图 D. Pareto chart 帕累托图 18. The practice of overlapping project activities is known as- 项目工作相互交错这一现象被认为是[ ] a. concurrent engineering 当前项目 b. Fast-tracking 快速跟进 c. Leveling 平衡 d. Crashing 赶工
|