1. You have decided to improve your leadship capability. Then you will choose what approach? A. to attend a PM training course B. to improve your technical knowledge C. to analysis PM's weakness and strength 2. About 30 percent of the team members has chosen to execute the early retirement plan option, and will be leaving the team. As a PM, what will you do first to deal with the situation? 3. You project has been initiated 3 months after schedule. You need additional resources and financial support to catch the time. You have talked several times with the sponsor on this question, but found he is not interested in it, and didn't want to solve the problem. Your project is in high risk now, what will you do? A. to report the situation to the sponsor's boss B. one is risk analysis and decide carry out project or termination 4. Both CPM and PERT bear the similarity that they assumes each activity duration is ...... A. is statistically independent estimates B. is statistically dependent estimates.