Please refer to the following information to answer questions 1 and 2. Robert was assigned as the project manager on a project with a clearly defined scope limited to the design-and-build phase of a product assembly line. A member of the client’s team has asked a functional supervisor on the project to complete a small job during the installation phase of the project. The functional supervisor referred the client to the project manager. 1.The BEST response to this request would require a review of information developed in which of the following sub-processes? A. Activity duration estimating B. Scope verification C. Scope definition D. Schedule development 2.Responding to this type of request requires: A. A revised resource plan. B. Approval by the project sponsor. C. A revised statement of work. D. A scope change control activity. 3. You are just hired by ABC Company as a project manager. It is seemed that the company does not support your project. The committed resources for the project are not provided, and the sponsor are not very much devoted to the project. To involve the sponsor in your project and help gain his/her support, you should: A. Update your sponsor when asked about status B. Provide your sponsor with regular status updates C. Address your concerns with the sponsor’s boss D. Ask your team members how to gain needed support 4. On a project, you measure a completed result against the design specifications. This is an example of a quality: A . Benchmark B . Assurance test C . Audit D . Control test 5. To determined if proposed modifications to the project baseline should be made, what should be put in place? A . A communication plan B . A quality assurance plan C . A change control system D . An issue management process