You are the project manager of the User Manual Project. The user manual your team is creating will be packaged with the office chairs your company makes. Nancy Martin, the Marketing Director and Sponsor of the project, requests that 30 additional pages be added to the user manual. These extra pages will describe the additional line of office products available through your company. What is your initial reaction to this proposed change? A. Approve the change as the project sponsor has made it. B. Deny the change as the project is already in the implementation phase. C. Approve the change if the budget can afford the expense. D. Deny the change as it falls outside of the project scope. 答案是D,但是我记得BOSON里的一道题目和此类似,也是SPONSOR要求PM修改工作范围,但是BOSON里的解释是发起人很重要,因为可能会涉及今后的项目分配或支持事宜,所以最好想办法解决。好像和这道题有些冲突。
|